Page 212 - Building Regulation Design Guidelines - Architecture Book (Blue Code)
P. 212

SEcTION: 19  REFUSE DISPOSAL REQUIREMENTS  SEcTION: 19  REFUSE DISPOSAL REQUIREMENTS



 19.3  RUBBISh cALcULATIONS AND DUMPSTERS MEASUREMENTS  19.4  DISPOSAL REQUIREMENTS FOR DIFFERENT TYPES OF BUILDINGS:

 19.3.1   The calculation of the daily garbage amount for different building   19.4.1   In hotel establishments, it is possible to provide a hydraulic
 uses shall be as follows:   compressor. This requires the submission of a special study, and

 19.3.1.1  Residential Use:  an average of 12 kg for each 100.0   the approval of the Authority.
 square meters of occupied area.
                     19.4.2   In educational establishments, a dumpster collection point must
 19.3.3.2  Commercial use:  be provided, that will accommodate not less than two of 2.5 cubic
                            meters dumpsters, one of them for papers and other for waste
 a)  Shopping Mall and Retail: an average of 12 kg for
 each 100.0 square meters of occupied area.  products.
 b)  Office:  an  average  of  5  kg  for  each  140.0  square   19.4.3   In health establishments, provision for a dumpster collection
 meters of occupied area.   point that will accommodate not less than two of 2.5 cubic meters
                            dumpsters is a must. This is in addition to containers for patient
 c)  Hotel: an average of 3 kg for each room, 5 kg for   rooms, offices and administrative area where garbage output
 each suite and for other areas according to the type   calculation is 12kg/day for every 100.0 square meters of the net
 of activities.
                            space area. Proper segregation shall be provided for the hospital
 19.3.2   The standard measurements for the garbage dumpsters   and the ordinary waste.
 (containers) as follows: (figure -80)
                     19.4.4   In staff accommodation, a dumpster collection point shall
 3
 a)  The measurements of a 1.1 *(m ) dumpster is 1.22   accommodate an average of one 2.5 cubic meters dumpster for
 x1.26 meter.               each 1000.0 square meters total building area in addition to the
                            garbage rooms each floors.
 b)  The measurements of a 2.5 *(m ) dumpster is 1.48 x
 3
 2.04 meter.         19.4.5   In industrial installations, a dumpster collection point must
                            be provided with an area that is at least 3 x 3 square meters.
                            It should be tiled with washable tiles, and a water supply for
                            washing.  The collection point should have accommodate the
                            number of dumpsters required, at an average of one 2.5 cubic
                            meters dumpster for each 2000.0 square meters of the building
                            total area.

                     19.4.6   In residential villas, in investment complexes, which consist of
                            a number of villas, a dumpster collection point shall be at an
                            average of one 2.5 cubic meters dumpster for every 10 villas.






 *m3 = cubic meters