SEcTION: 19  REFUSE DISPOSAL REQUIREMENTS  SEcTION: 19  REFUSE DISPOSAL REQUIREMENTS




 ≥ 0.3 m  ≥ 0.3 m  19.2  GARBAGE chUTES

 Garbage             19.2.1   For buildings with more than three stories a garbage chute shall
 Trolleys
 Capacity                   be installed.
 2.5 *(m3)
                     19.2.2   The materials for the garbage chute shall be non-corrosive, non-
 2.04 m                     combustible, prevent dampness, and have smooth inner surface.

 1.48 m              19.2.3   The minimum chute diameter shall be 0.6 meter inside the small
                            room of not less than 0.9 x 0.9 meter in size. Door of minimum
 ≥ 0.3 m                    0.8 meter wide, opening outwards with an automatic closing

 1.22 m                     mechanism shall be fitted to all typical floors.
 Internal
 Corridor  1.26 m  Garbage  19.2.4   For plot area less than 1500.0 square meters, the garbage chute
 Trolleys
 Capacity                   can be replaced by a small room 1.8 x 1.2 meter on each floor in
 ≥ 1.2 m  1.1 *(m3)         addition to the main garbage room on the ground floor.
 ≥ 0.6 m  ≥ 1.8 m           The doors shall be 0.9 meter minimum width opening outwards
                            and shall have an automatic door closing mechanism and
                            mechanical ventilation.
 ≥ 1.2 m             19.2.5   Service elevator located separately from the main building’s

                            elevators lobby, close to the garbage room at the ground floor
                            can replace the garbage chute in addition to the small room in
                            each floor of not less than the size of the service elevator.
 Ramp
                     19.2.6   The owner of the building or the authorized representative is
  slope ≤ 8%                responsible for cleaning the building internally and externally,
                            together with the surrounding area to the public road.
 Figure-80   Garbage Room Mearsurements
                     19.2.7   If the location of the chute is far from the road surrounding the
                            plot, the garbage collection room shall be located near to the
                            road, or alleyway in case of non- existence of a road.

                     19.2.8   Active chemical waste, liquids and /or any other hazardous toxic
                            materials shall not be place inside the garbage dumpsters or
                            containers.



 *m3 = cubic meters