SEcTION: 3  ARCHITECTURAL SUBMITTAL REQUIREMENTS                                    SEcTION: 3  ARCHITECTURAL SUBMITTAL REQUIREMENTS



                3.3  REVISIONS STAGE                                                                          3)  A  copy  of  the  latest  approved  architectural  drawings  by  the
                                                                                                                 Authority shall be attached for reference.
                    Revisions  are submittals  of any  modification  from  previous approved
                    drawings during construction stage before issuing Building Completion                     4)  Scale of drawings shall be as mentioned previously.
                    Certificate (BCC) comprises architectural revised drawings along with
                    approved drawings by the Authority.
                    For  revisions  after  Building  Completion  Certificate (BCC)  please  refer  to
                    Authority Workflow.
                    In case the submission is a revision or an alteration during construction
                    stage no need for registration on e-permit. Only submittal of soft copy of
                    revised drawings along with documents is required.

                    3.3.1  Documentation:
                          1)  Title sheet with project name and Owner/s name, plot number,
                             accumulated area schedule, total built-up, car park areas,
                             coverage area, etc., with revisions highlighted from the
                             approved.
                          2)  Document  sheets  composed  of  affection  plan,  consultant’s
                             appointment letter, trade license, building permit letter and
                             other documents as required.

                          3)  Owner’s signature on the title sheet, revised detailed area
                             calculations sheet, and main setting out / development plans.
                          4)  Consultant’s stamp and signature shall appear on all sheets of
                             digital drawings.
                          5)  In case of revisions in car park area, garbage and sanitation;
                             revised calculations and criteria shall be re-submitted
                             highlighting the changes from the approved.

                    3.3.2  Architectural Drawings:
                          1)  The affected areas on already approved drawings to be
                             highlighted  in yellow and revised  areas to be highlighted
                             in red.
                          2)  Any revision shall be submitted on all related drawings such as
                             plan, section and details.


           34                                                                                                                                                35